Easy Construction Management Scheduling & Control
What is the critical path in project scheduling?
Answer
The critical path is the longest sequence of dependent activities determining minimum project duration. Activities on critical path have zero float - any delay directly extends project completion. Non-critical activities have float (slack time) allowing schedule flexibility. Critical path method (CPM) calculates early/late start and finish dates for each activity to identify critical path. Project managers focus on critical activities for schedule control, as delays there impact project completion date.
IIT Certified
Master These Concepts with IIT Certification
175+ hours of industry projects. Get placed at Bosch, Tata Motors, L&T and 500+ companies.
Relevant for Roles
Project Scheduler Project Manager Construction Manager