Easy Construction Management Scheduling & Control

What is the critical path in project scheduling?

Answer

The critical path is the longest sequence of dependent activities determining minimum project duration. Activities on critical path have zero float - any delay directly extends project completion. Non-critical activities have float (slack time) allowing schedule flexibility. Critical path method (CPM) calculates early/late start and finish dates for each activity to identify critical path. Project managers focus on critical activities for schedule control, as delays there impact project completion date.