What are the methods for construction delay analysis?

Answer

Delay analysis methods: (1) As-planned vs as-built - compare original schedule to actual, simple but doesn't consider concurrency, (2) Impacted as-planned - add delays to as-planned schedule, shows delay impact, (3) Collapsed as-built - remove delays from as-built, shows but-for duration, (4) Time impact analysis - insert delays into schedule updates contemporaneously, most accurate, (5) Windows analysis - divide project into periods, analyze each window. Selection depends on schedule quality, documentation, and claim requirements. Analysis requires understanding of critical path and concurrent delays.

Master These Concepts with IIT Certification
IIT Certified

Master These Concepts with IIT Certification

175+ hours of industry projects. Get placed at Bosch, Tata Motors, L&T and 500+ companies.

Relevant for Roles

Scheduler Claims Analyst Project Manager