What is the Total Cost Method for calculating construction damages?

Answer

Total Cost Method calculates damages as difference between actual cost and bid cost, attributing all overrun to owner-caused issues. Used only when: (1) Other methods impractical due to documentation limitations, (2) Bid was reasonable, (3) Actual costs reasonable and documented, (4) Contractor not responsible for overrun. Weaknesses: doesn't separate owner-caused from contractor inefficiency, bidding errors, or other causes. Modified total cost accounts for contractor-responsibility costs. Measured mile or other comparative methods preferred when documentation allows specific damage calculation.

Master These Concepts with IIT Certification
IIT Certified

Master These Concepts with IIT Certification

175+ hours of industry projects. Get placed at Bosch, Tata Motors, L&T and 500+ companies.

Relevant for Roles

Claims Consultant Senior Project Manager Forensic Accountant